Budget

The proposed budget at the end of fall quarter was $59.28. Due to corrected errors and design changes, the planned budget further increased to $71.28 on 1/28/20, $89.24 on 2/03/20, and finally to $128.64 on 2/10/20. The actual expenditure as of 2/28/20 was $172.17, which accounts for tax & shipping. Fortunately, there were no additional costs during the testing in Spring quarter.

​

The total number of parts is 161; there are 95 3D-printed plastic parts (20 unique ones), 50 screws (3 sizes), 10 nuts (2 sizes), and 6 springs (3 sizes). Click Here to See The Latest Budget 

​

budget_42920.PNG
Budget & Schedule: Text

Schedule

The milestones for the project over the entire year are shown below. All analysis, construction, and testing are completed. The entire project is currently complete, with 668 labor hours to date. Click Here to See Schedule

schduel_website_2.png